Owner’s representation for a superyacht new build.

From design review through construction and specialist inspections to final outfitting, trials and handover, with the Chief Engineer involved early.

The three phases of a new build.

Specialists are engaged where their expertise is needed, for the agreed scope and period. The timing of each phase follows the project programme.

An illustrative example: a 51-month new build

  1. Control setup and design review

    Months 1 to 8

  2. Construction interfaces and specialist inspections

    Months 9 to 39

  3. Final outfitting, trials and handover

    Months 40 to 51

Continuous throughout the mandate

  • Owner’s representation
  • Project coordination
  • Financial & change control
  • Reporting to the Owner

What is watched, and when.

Technical survey continues throughout, with site visits under the agreed inspection plan. Design coordination moves from review to onboard conformity, and delivery readiness builds towards handover.

In the same example
Track Detail When
Technical survey
  • Design / hull survey
  • Pre-outfitting
  • Yard outfitting
  • Trials
Continuous, with changing focus, months 1 to 51
Design coordination & interior conformity
  • Design review
  • Workshop and onboard conformity / quality
Design review in months 1 to 8; conformity from month 15
Delivery readiness & handover
  • Preparation
  • Handover focus
Months 40 to 51
Chief Engineer
  • ASYA-managed, separately Owner-funded
Early involvement, in this example from month 28

Timing and attendance are agreed in the written mandate.

A Chief Engineer appointed early knows the yacht before delivery.

Managed and coordinated by ASYA, funded separately by the Owner.

When the Chief Engineer joins, and how intensively, is defined for each project.

  • During construction

    System knowledge and build familiarisation

  • At delivery

    Manuals, spares, training and handover conditions

  • In operation

    Continuity onboard and informed warranty follow-up

Any ASYA post-delivery services require a separate agreement.

The work, area by area.

Each area has a lead and a defined coverage across the programme. Activity types describe recurring work — not task volumes or hours.

Open an area to see its activity types, lead and coverage.

Months as in the same example.

  1. 01 Owner’s representation , months 1 to 51
    • 1.1Owner priorities and brief
    • 1.2Decision options and recommendations
    • 1.3Escalation and adviser coordination
    Lead
    Owner’s Representative
    Coverage
    months 1 to 51
  2. 02 Project coordination , months 1 to 51
    • 2.1Programme and dependencies
    • 2.2Actions and blocker follow-up
    • 2.3Yard, designer and supplier interfaces
    Lead
    Owner’s Representative initially, then the mandate’s Project Manager
    Coverage
    months 1 to 51
  3. 03 Financial & change control , months 1 to 51
    • 3.1Baseline and forecast exposure
    • 3.2Variations, credits and items supplied by the Owner
    • 3.3Evidence review for authorised decisions
    Lead
    Owner’s Representative, with a specialist reviewer engaged for the mandate
    Coverage
    months 1 to 51
  4. 04 Technical survey , months 1 to 51
    • 4.1Specifications, drawings and interfaces
    • 4.2Inspections under the agreed plan
    • 4.3Findings, tests and completion evidence
    Lead
    Technical supervision
    Coverage
    months 1 to 51
  5. 05 Design coordination , Design to handover
    • 5.1Layouts, materials and samples
    • 5.2Workshop and onboard conformity
    • 5.3Interior snagging and completion evidence
    Lead
    Design coordination, conformity and quality control
    Coverage
    Design to handover · conformity from month 15
  6. 06 AI agent coordination & QA , months 1 to 51
    • 6.1Sources organised and prepared for AI tools
    • 6.2Human QA and specialist checks before release
    • 6.3Dashboard and daily / weekly briefs
    Lead
    AI coordinator with human reviewers
    Coverage
    months 1 to 51
  7. 07 Delivery readiness , Final focus months 40 to 51
    • 7.1Readiness plan and evidence dossier
    • 7.2Manuals, spares and training coordination
    • 7.3Handover package and remaining issues
    Lead
    Project Manager, specialists and Chief Engineer
    Coverage
    Progressive preparation · final focus months 40 to 51

Visits and capacity are agreed per mandate.

The seven areas serve four controls, the same for a new build and a refit: Owner’s representation and coordination, technical and design oversight, financial and change control, and delivery readiness and handover.

One continuous mandate, from appointment to handover.

Specialists join for defined work packages; Luigi Adamo leads the Owner’s representation throughout.

Choosing an Owner’s Representative.

Discuss your project with Luigi Adamo.